Bathroom remodeling contractors in Somerville, MA

Somerville is the most densely populated city in New England, and that drives cost: tight lots, shared walls, permit parking for dumpsters, and Boston-area labor rates. Prices track Cambridge closely.

Our Haus isn't a contractor directory. We give you the local cost math, the permit reality, and the paperwork tools — the scope, the proposal comparison, and the vault your records live in.

Bathroom remodel cost in Somerville

Based on a 60 sq ft bathroom remodel scope, adjusted by the Massachusetts regional cost index and a Somerville metro multiplier of 1.10×. A 10% contingency reserve is included. These are budgeting estimates, not quotes.

Source: Our Haus baseline estimates per square foot, adjusted with a Massachusetts cost index and a Somerville metro factor.
Somerville bathroom remodelLowLikelyHigh
Basic finishEntry-level materials, no layout change$17k$24k$33k
Mid-range finishThe most common scope$33k$45k$62k
High-end finishCustom materials and detail$62k$81k$114k

Source: Our Haus baseline estimates per square foot, adjusted with a Massachusetts cost index and a Somerville metro factor.

Estimated range — based on BLS OEWS national average wages and BLS PPI material indexes applied to Our Haus baseline unit costs, as of June 2026. Estimates are shown as a range and help set expectations. They are not a quote, a verified price, or an appraisal of what a contractor will charge.

Where the money goes (mid-range finish)

Line item
Line itemLowLikelyHigh
Tile & shower/tub$6.7k$9.0k$12k
Vanity & countertop$3.6k$4.9k$6.7k
Plumbing fixtures$4.2k$5.7k$7.9k
Flooring$2.1k$2.9k$3.9k
Electrical & lighting$1.8k$2.5k$3.4k
Drywall, paint, trim$2.1k$2.9k$3.9k
Labor (general)$8.5k$11k$16k
Permits & design$1.2k$1.6k$2.2k

Estimated range — based on BLS OEWS national average wages and BLS PPI material indexes applied to Our Haus baseline unit costs, as of June 2026. Estimates are shown as a range and help set expectations. They are not a quote, a verified price, or an appraisal of what a contractor will charge.

What drives the price in Somerville

Triple-deckers and two-families built from the 1890s through the 1920s make up most of the city, many now split into condominiums. Expect balloon framing, plaster and lath, old steam heat, shared utilities, and lead-safe work rules on almost every job.

Tile scope and size
Labor scales with the number of cuts, not just the area. Large-format tile, herringbone layouts, niches, and curbless entries all raise the labor line well above a simple 12x24 floor.
Moving plumbing
Keeping the toilet, sink, and shower in place keeps the job in the low band. Moving the toilet is the single most expensive fixture move because of the waste line.
Tub-to-shower conversion
Common in older New England homes, and it usually means reframing the floor, resetting the drain, and full waterproofing rather than a swap.
Ventilation
Many older bathrooms have no fan or vent into an attic. Adding a properly sized fan ducted to the exterior is inexpensive and prevents the mold problem that causes the next remodel.
Hidden water damage
In pre-1950 homes, a failed shower pan has often been leaking quietly for years. Budget contingency here specifically.

Common Somerville neighborhoods where this work comes up: Davis Square, Union Square, Teele Square, Winter Hill, Spring Hill, Ten Hills.

Permits and rules in Somerville

Authority: City of Somerville Inspectional Services Department, Building Division

Building permits are filed through the city's online portal, with separate trade permits. Demolishing a building over 75 years old goes through Demolition Review first. Properties in a local historic district need Historic Preservation Commission approval for exterior repairs and alterations. In condominium buildings, check the association's approval rules before booking a contractor.

Massachusetts contract and licensing rules

Same Massachusetts rules as Boston: written contract over $1,000, Home Improvement Contractor registration, one-third deposit cap, and required start and completion dates in the contract.

Timeline and season in Somerville

Exterior work runs April through November. Street access and parking are tighter than the calendar, so dumpster and delivery permits need to be lined up early in the busy spring and summer months.

Typical duration: 3–6 weeks on site.

  1. 1
    Design and selections · 1–3 weeks

    Fixture and tile selection. Order everything before demolition — a backordered valve stops the whole job.

  2. 2
    Permitting · 1–3 weeks

    Plumbing and electrical permits; a building permit if framing changes.

  3. 3
    Demolition · 1–2 days

    Down to studs. Subfloor and framing condition is assessed here.

  4. 4
    Rough-in and inspection · 3–5 days

    Plumbing and electrical rough, fan duct, blocking for grab bars, then inspection.

  5. 5
    Waterproofing and tile · 1–2 weeks

    Backer board, waterproof membrane, pan slope, then tile and grout with cure time between steps.

  6. 6
    Fixtures and finish · 3–5 days

    Vanity, toilet, trim, glass measurement — shower glass is typically ordered after tile is set and adds 1–2 weeks.

What's included — and what usually isn't

Bathrooms are small but dense: plumbing, waterproofing, tile, ventilation, and electrical all land in a few dozen square feet. Cost per square foot runs higher than almost any other room, and the difference between a good and a bad job is mostly invisible waterproofing work.

Typically included

  • • Demolition down to studs and subfloor where tile is being replaced
  • • Waterproofing and shower pan or tub set
  • • Tile — floor, shower walls, and any accent work
  • • Vanity, countertop, mirror, and storage
  • • Plumbing fixtures: toilet, shower valve, trim, and drains
  • • Exhaust fan sized to the room and vented outside
  • • Electrical: GFCI protection, lighting, and any heated-floor circuit
  • • Paint and trim

Usually excluded

  • • Rotted subfloor or joist repair found at demolition
  • • Relocating the toilet drain, which usually means opening the ceiling below
  • • Whole-house water pressure or supply-line issues
  • • Mold remediation behind an existing failed shower

What a complete Somerville estimate spells out

  • • The waterproofing system by name (sheet membrane, liquid membrane, or a proprietary system)
  • • Tile allowance in dollars per square foot, supply only, with quantity
  • • Fixture model numbers or a per-fixture allowance
  • • Whether shower glass is included and when it is measured
  • • Exhaust fan CFM and where it vents
  • • A stated unit price for subfloor or joist repair if it is found

Full checklist: what should be in a contractor's estimate.

Looking for a bathroom remodel contractor in Somerville?

We don't keep a contractor directory, and we won't pretend to. The dependable process is to gather two or three referrals locally, check the Massachusetts registration or license rules above, confirm general liability and workers' compensation directly with each carrier, then compare the written proposals side by side against the ranges on this page.

Run a Somerville contractor's business? You can publish a free Our Haus profile with your license, insurance dates, service area, and work photos, and share it by link or QR code.

Have a Somerville quote in hand?

Run it through the quote range checker. We compare it against the Massachusetts cost index, flag line items that look high, and review the contract against Massachusetts home-improvement rules.

Check my quote

Bathroom remodel in Somerville — common questions

Why do small bathrooms cost so much per square foot?

Every trade has to work in the same tiny room in sequence, and the fixed costs — permits, waterproofing, a shower valve, a vanity, a toilet — do not shrink with the room. A 40-square-foot bathroom and a 70-square-foot bathroom often differ by only a few thousand dollars in total.

How long will I be without the bathroom?

Plan on the full on-site duration, typically three to six weeks. Cure times for mortar, waterproofing, and grout are not compressible, and shower glass usually arrives a week or two after tile is finished.