Kitchen remodeling contractors in Boston, MA

Boston is one of the most expensive renovation markets in the country. Dense parcels, narrow streets, permit parking for dumpsters and deliveries, and a deep bench of union-scale trades all push labor above the Massachusetts average — often before a single material decision is made.

Our Haus isn't a contractor directory. We give you the local cost math, the permit reality, and the paperwork tools — the scope, the proposal comparison, and the vault your records live in.

Kitchen remodel cost in Boston

Based on a 150 sq ft kitchen remodel scope, adjusted by the Massachusetts regional cost index and a Boston metro multiplier of 1.12×. A 10% contingency reserve is included. These are budgeting estimates, not quotes.

Source: Our Haus cost engine — per-square-foot bands from public industry data (Cost vs. Value, NAHB, RSMeans-derived regional indices), adjusted for Massachusetts and the Boston metro. Refreshed annually.
Boston kitchen remodelLowLikelyHigh
Basic finishEntry-level materials, no layout change$36k$48k$67k
Mid-range finishThe most common scope$67k$91k$121k
High-end finishCustom materials and detail$121k$169k$242k

Source: Our Haus cost engine — per-square-foot bands from public industry data (Cost vs. Value, NAHB, RSMeans-derived regional indices), adjusted for Massachusetts and the Boston metro. Refreshed annually.

Estimated range — based on BLS OEWS national average wages and BLS PPI material indexes applied to Our Haus baseline unit costs, as of June 2026. Estimates are shown as a range and help set expectations. They are not a quote, a verified price, or an appraisal of what a contractor will charge.

Where the money goes (mid-range finish)

Line item
Line itemLowLikelyHigh
Cabinets$18k$24k$32k
Countertops$6.1k$8.3k$11k
Appliances$8.5k$12k$15k
Flooring$4.2k$5.8k$7.7k
Plumbing & fixtures$4.8k$6.6k$8.8k
Electrical & lighting$3.6k$5.0k$6.6k
Drywall, paint, trim$3.6k$5.0k$6.6k
Labor (general)$9.7k$13k$18k
Permits & design$2.4k$3.3k$4.4k

Estimated range — based on BLS OEWS national average wages and BLS PPI material indexes applied to Our Haus baseline unit costs, as of June 2026. Estimates are shown as a range and help set expectations. They are not a quote, a verified price, or an appraisal of what a contractor will charge.

What drives the price in Boston

Much of the city's housing predates 1940: South End and Back Bay brownstones, Dorchester and Jamaica Plain triple-deckers, and Victorians in Roslindale and West Roxbury. Expect knob-and-tube remnants, balloon framing, plaster-and-lath walls, cast-iron waste stacks, and lead paint in anything built before 1978 — all of which add scope that a per-square-foot average never captures.

Cabinet tier
Cabinets are typically the single largest line item — often close to a third of the job. Moving from stock to semi-custom to full custom can double the cabinet line by itself.
Layout changes
Keeping sink, range, and refrigerator in place is the cheapest kitchen you can build. Moving the sink means new supply and waste runs; moving a gas range means a new gas line and often a new vent path.
Wall removal
Opening a kitchen to a living space usually means a load-bearing header, temporary shoring, and an engineer's letter for the permit. In older homes it also means finding out what is inside the wall.
Electrical service
Older homes frequently cannot support an induction range, a wall oven, and a microwave without a panel upgrade. That is a separate line item and a separate permit.
Countertop material
Laminate, butcher block, quartz, and natural stone span a wide range, and stone adds template and fabrication lead time between demo and finish.

Common Boston neighborhoods where this work comes up: Back Bay, South End, Jamaica Plain, Dorchester, Charlestown, South Boston.

Permits and rules in Boston

Authority: City of Boston Inspectional Services Department (ISD)

Long-form building permits are required for structural work, additions, and most layout changes; short-form permits cover like-for-like interior work. Electrical and plumbing permits are pulled separately by the licensed trade. Landmark districts (Back Bay, Beacon Hill, South End, Bay Village, Mission Hill Triangle) add a Boston Landmarks Commission or district-commission review before exterior work, which routinely adds weeks to the front of a schedule.

Massachusetts contract and licensing rules

Massachusetts requires a written contract for residential work over $1,000, and the contractor must be registered under the Home Improvement Contractor (HIC) program. The contract must state the total price, a payment schedule, start and completion dates, and the contractor's HIC registration number. Deposits are capped at one third of the total price (or the cost of special-order materials, whichever is greater).

Timeline and season in Boston

Exterior work concentrates between April and November. Roofing shingles need surface temperatures above roughly 40°F to seal properly, so late-fall installs often run a hand-sealing step. Foundation and excavation work slows once the ground freezes, and spring is the busiest booking window — quotes issued in January are usually cheaper than the same scope quoted in May.

Typical duration: 8–14 weeks on site once materials are in hand.

  1. 1
    Design and selections · 2–6 weeks

    Layout, cabinet order, and every finish selection. Cabinet lead time drives the whole schedule — order before demolition.

  2. 2
    Permitting · 1–4 weeks

    Building permit plus separate electrical and plumbing permits. Historic-district review, where it applies, sits in front of this.

  3. 3
    Demolition · 2–4 days

    The scope-change window. Anything hidden — rot, old wiring, undersized framing — surfaces here.

  4. 4
    Rough-in · 1–2 weeks

    Framing changes, plumbing and electrical rough, inspections before anything is closed up.

  5. 5
    Drywall and paint prep · 1 week

    Board, tape, prime. Dust travels through the whole house during this phase.

  6. 6
    Cabinets and counters · 1–3 weeks

    Cabinets install, then counters are templated and fabricated — usually a 1–2 week gap before the stone arrives.

  7. 7
    Finishes and punch list · 1–2 weeks

    Backsplash, appliances, trim, lighting, final inspections, and the punch list.

What's included — and what usually isn't

A full kitchen remodel replaces cabinets, counters, appliances, flooring, and lighting, and usually touches plumbing and electrical. The spread between a modest refresh and a gut renovation with a moved wall is the widest of any room in the house.

Typically included

  • Demolition and disposal of existing cabinets, counters, and flooring
  • Cabinetry — stock, semi-custom, or custom, plus installation
  • Countertops, backsplash, and sink cutouts
  • Appliance rough-in and installation
  • Plumbing fixtures and any supply or waste relocation
  • Electrical: circuits for appliances, under-cabinet and ceiling lighting, code-required GFCI outlets
  • Flooring, drywall repair, trim, and paint

Usually excluded

  • Appliance purchase, when the contract lists it as an allowance rather than a supplied item
  • Structural work to remove a wall (priced separately once an engineer sizes the beam)
  • Panel upgrades required to add appliance circuits
  • Asbestos or lead abatement discovered during demolition

What a complete Boston estimate spells out

  • Cabinet manufacturer, line, and door style — not just "new cabinets"
  • Countertop material and a square-foot figure, with edge profile named
  • Appliance allowance as a dollar figure, or the model numbers being supplied
  • Who supplies and who installs each item
  • Whether the price includes disposal, protection of adjacent rooms, and final cleaning
  • A change-order clause with a stated markup

Full checklist: what should be in a contractor's estimate.

Have a Boston quote in hand?

Run it through the quote range checker. We compare it against the Massachusetts cost index, flag line items that look high, and review the contract against Massachusetts home-improvement rules.

Check my quote

Kitchen remodel in Boston — common questions

How much does a kitchen remodel cost in Boston?

For a typical 150-square-foot Boston kitchen at a mid-range finish, plan on the range in the table above. Boston runs roughly 12 percent above the Massachusetts average because of labor rates and site logistics — permit parking for a dumpster, no driveway to stage materials, and stair-carry on triple-deckers and brownstones all show up in the labor line.

Do I need a permit for a kitchen remodel in Boston?

Yes for anything beyond a cosmetic swap. Boston ISD issues a short-form permit for like-for-like interior work and a long-form permit when you change layout or structure. Electricians and plumbers pull their own permits. In Back Bay, Beacon Hill, the South End, and other landmark districts, exterior changes need commission review first.

What surprises come up in old Boston kitchens?

Knob-and-tube remnants, undersized service that cannot carry a modern range and wall oven, plaster-and-lath that does not survive cabinet removal, cast-iron waste lines, and floors out of level enough to matter when a stone countertop goes in. Budget contingency above the standard 10 percent in anything built before 1940.

Does Massachusetts require a written contract?

Yes — over $1,000 the contract must be written, must carry the contractor's Home Improvement Contractor registration number, and must include a payment schedule with start and completion dates. Deposits are capped at one third of the total price.

How long does a Boston kitchen remodel take?

Eight to fourteen weeks on site once materials are in hand, plus cabinet lead time of six to twelve weeks before that, plus permit review. Landmark-district projects should add several weeks at the front for commission review.

Should I order cabinets before demolition?

Yes. Cabinet lead times commonly run six to twelve weeks, and demolishing a working kitchen before the cabinets are in the shop turns a schedule gap into weeks without a kitchen.

Is a kitchen remodel worth it at resale?

Industry cost-versus-value data consistently shows minor and mid-range kitchen remodels recovering a larger share of their cost than high-end ones. A $30,000 refresh usually returns a better ratio than a $120,000 gut, even though the gut may be the right call for how you live.