Kitchen remodeling contractors in Quincy, MA

Quincy sits in the Boston labor market but prices a little below the city and the inner western suburbs. Driveways and yards make staging easier than in Boston, while the long shoreline adds flood rules that change what a renovation can include.

Our Haus isn't a contractor directory. We give you the local cost math, the permit reality, and the paperwork tools — the scope, the proposal comparison, and the vault your records live in.

Kitchen remodel cost in Quincy

Based on a 150 sq ft kitchen remodel scope, adjusted by the Massachusetts regional cost index and a Quincy metro multiplier of 1.02×. A 10% contingency reserve is included. These are budgeting estimates, not quotes.

Source: Our Haus baseline estimates per square foot, adjusted with a Massachusetts cost index and a Quincy metro factor.
Quincy kitchen remodelLowLikelyHigh
Basic finishEntry-level materials, no layout change$33k$44k$61k
Mid-range finishThe most common scope$61k$83k$110k
High-end finishCustom materials and detail$110k$154k$220k

Source: Our Haus baseline estimates per square foot, adjusted with a Massachusetts cost index and a Quincy metro factor.

Estimated range — based on BLS OEWS national average wages and BLS PPI material indexes applied to Our Haus baseline unit costs, as of June 2026. Estimates are shown as a range and help set expectations. They are not a quote, a verified price, or an appraisal of what a contractor will charge.

Where the money goes (mid-range finish)

Line item
Line itemLowLikelyHigh
Cabinets$16k$22k$29k
Countertops$5.5k$7.5k$10k
Appliances$7.7k$11k$14k
Flooring$3.9k$5.3k$7.0k
Plumbing & fixtures$4.4k$6.0k$8.0k
Electrical & lighting$3.3k$4.5k$6.0k
Drywall, paint, trim$3.3k$4.5k$6.0k
Labor (general)$8.8k$12k$16k
Permits & design$2.2k$3.0k$4.0k

Estimated range — based on BLS OEWS national average wages and BLS PPI material indexes applied to Our Haus baseline unit costs, as of June 2026. Estimates are shown as a range and help set expectations. They are not a quote, a verified price, or an appraisal of what a contractor will charge.

What drives the price in Quincy

Early-1900s single-families and two-families in Wollaston and North Quincy, capes and colonials in the inland neighborhoods, and former summer cottages converted to year-round homes along the shore in Houghs Neck and Squantum. Older shore houses often sit on shallow foundations and need drainage and envelope work.

Cabinet tier
Cabinets are typically the single largest line item — often close to a third of the job. Moving from stock to semi-custom to full custom can double the cabinet line by itself.
Layout changes
Keeping sink, range, and refrigerator in place is the cheapest kitchen you can build. Moving the sink means new supply and waste runs; moving a gas range means a new gas line and often a new vent path.
Wall removal
Opening a kitchen to a living space usually means a load-bearing header, temporary shoring, and an engineer's letter for the permit. In older homes it also means finding out what is inside the wall.
Electrical service
Older homes frequently cannot support an induction range, a wall oven, and a microwave without a panel upgrade. That is a separate line item and a separate permit.
Countertop material
Laminate, butcher block, quartz, and natural stone span a wide range, and stone adds template and fabrication lead time between demo and finish.

Common Quincy neighborhoods where this work comes up: Wollaston, North Quincy, Quincy Point, Houghs Neck, Squantum, Merrymount, West Quincy.

Permits and rules in Quincy

Authority: City of Quincy Inspectional Services Department

Building permits are filed online, with separate electrical, plumbing, and gas permits pulled by licensed trades. Properties in the FEMA flood zone fall under the city's Floodplain Overlay District, which sets construction requirements for additions and major renovations. The department also runs free weekly clinics where homeowners can ask building, zoning, and conservation questions before applying.

Massachusetts contract and licensing rules

Same Massachusetts rules as Boston: written contract over $1,000, Home Improvement Contractor registration, one-third deposit cap, and required start and completion dates in the contract.

Timeline and season in Quincy

Exterior work runs April through November. Coastal storms in late fall and winter are a real scheduling risk for roof and siding work near the water, and spring quotes fill quickly once the season opens.

Typical duration: 8–14 weeks on site once materials are in hand.

  1. 1
    Design and selections · 2–6 weeks

    Layout, cabinet order, and every finish selection. Cabinet lead time drives the whole schedule — order before demolition.

  2. 2
    Permitting · 1–4 weeks

    Building permit plus separate electrical and plumbing permits. Historic-district review, where it applies, sits in front of this.

  3. 3
    Demolition · 2–4 days

    The scope-change window. Anything hidden — rot, old wiring, undersized framing — surfaces here.

  4. 4
    Rough-in · 1–2 weeks

    Framing changes, plumbing and electrical rough, inspections before anything is closed up.

  5. 5
    Drywall and paint prep · 1 week

    Board, tape, prime. Dust travels through the whole house during this phase.

  6. 6
    Cabinets and counters · 1–3 weeks

    Cabinets install, then counters are templated and fabricated — usually a 1–2 week gap before the stone arrives.

  7. 7
    Finishes and punch list · 1–2 weeks

    Backsplash, appliances, trim, lighting, final inspections, and the punch list.

What's included — and what usually isn't

A full kitchen remodel replaces cabinets, counters, appliances, flooring, and lighting, and usually touches plumbing and electrical. The spread between a modest refresh and a gut renovation with a moved wall is the widest of any room in the house.

Typically included

  • • Demolition and disposal of existing cabinets, counters, and flooring
  • • Cabinetry — stock, semi-custom, or custom, plus installation
  • • Countertops, backsplash, and sink cutouts
  • • Appliance rough-in and installation
  • • Plumbing fixtures and any supply or waste relocation
  • • Electrical: circuits for appliances, under-cabinet and ceiling lighting, code-required GFCI outlets
  • • Flooring, drywall repair, trim, and paint

Usually excluded

  • • Appliance purchase, when the contract lists it as an allowance rather than a supplied item
  • • Structural work to remove a wall (priced separately once an engineer sizes the beam)
  • • Panel upgrades required to add appliance circuits
  • • Asbestos or lead abatement discovered during demolition

What a complete Quincy estimate spells out

  • • Cabinet manufacturer, line, and door style — not just "new cabinets"
  • • Countertop material and a square-foot figure, with edge profile named
  • • Appliance allowance as a dollar figure, or the model numbers being supplied
  • • Who supplies and who installs each item
  • • Whether the price includes disposal, protection of adjacent rooms, and final cleaning
  • • A change-order clause with a stated markup

Full checklist: what should be in a contractor's estimate.

Looking for a kitchen remodel contractor in Quincy?

We don't keep a contractor directory, and we won't pretend to. The dependable process is to gather two or three referrals locally, check the Massachusetts registration or license rules above, confirm general liability and workers' compensation directly with each carrier, then compare the written proposals side by side against the ranges on this page.

Run a Quincy contractor's business? You can publish a free Our Haus profile with your license, insurance dates, service area, and work photos, and share it by link or QR code.

Have a Quincy quote in hand?

Run it through the quote range checker. We compare it against the Massachusetts cost index, flag line items that look high, and review the contract against Massachusetts home-improvement rules.

Check my quote

Kitchen remodel in Quincy — common questions

Should I order cabinets before demolition?

Yes. Cabinet lead times commonly run six to twelve weeks, and demolishing a working kitchen before the cabinets are in the shop turns a schedule gap into weeks without a kitchen.

Is a kitchen remodel worth it at resale?

Industry cost-versus-value data consistently shows minor and mid-range kitchen remodels recovering a larger share of their cost than high-end ones. A $30,000 refresh usually returns a better ratio than a $120,000 gut, even though the gut may be the right call for how you live.